Free BOQ Template for Building Construction (Excel)
Download a free bill of quantities (BOQ) template in Excel, ready for a house or small building. Rate and amount work out themselves, each section totals to a summary with overhead, provisional sums, contingency and tax, and there is a filled example for a three-bedroom house. No email or sign-up.
By Aaghaz360 teamReviewed
Download the BOQ template
Excel (.xlsx), works in Excel, Google Sheets, Numbers and LibreOffice.
Rather price it online? The free BOQ generator fills in default material and labour rates for eight countries and exports a priced BOQ to Excel.
Open the BOQ generatorWhat's in the BOQ template
One Excel sheet with the standard BOQ columns, eleven house sections in build order, live formulas for rate, amount and section totals, and a summary that adds overhead, provisional sums, contingency and tax.
- Columns: Ref, Description, Unit, Qty, Material rate, Labour rate, Rate (material + labour), Amount (qty × rate) and Notes.
- Sections: Preliminaries, Substructure, Frame and upper floors, Roof, Stairs, External walls, Windows and external doors, Internal walls and doors, Internal finishes, Services, External works.
- Summary: each section total, overhead and profit (%), provisional sums for fees and utility connections, a prime cost sum, contingency (%) and tax (%).
- Shaded cells are the ones you fill. Everything else calculates, so add or delete rows inside a section and the totals still hold.
How to prepare a BOQ in Excel
Measure each item from the drawings, enter the quantity and unit, price it with a material and a labour rate, and let each section total carry to the summary, where you add overhead, provisional sums, contingency and tax.
- Fill in the project details and choose your currency before you download.
- Take off quantities from the drawings, section by section, using one method of measurement. Measure net: wall area less openings, for example.
- Enter a material rate and a labour rate per unit from supplier and subcontractor quotes. The template adds them and works out the amount.
- Add provisional sums for work you can’t describe yet and prime cost sums for items not chosen yet, such as kitchen units.
- Set overhead, contingency and tax percentages in the summary. The total updates as you go.
Our guide to quantity takeoff and unit costs works through a foundation example step by step.
Standard BOQ format
A bill of quantities lists each item of work with a reference, a description, a unit, a quantity, a rate and an amount, grouped into sections whose totals carry to a summary.
| Column | What goes in it |
|---|---|
| Ref | A unique item reference, such as B.3 |
| Description | What the work is, referring to the specification rather than repeating it |
| Unit | m, m², m³, t, nr (number), item or hour |
| Quantity | Measured net from the drawings |
| Rate | The price per unit, entered by whoever prices the bill |
| Amount | Quantity × rate, totalled per section |
A full bill also has preliminaries (the contractor’s site-wide costs such as set-up, supervision and insurance), provisional and prime cost sums, daywork rates for unmeasured work, and a summary (BOQ format conventions).
BOQ sections for a house, in build order
The template follows the element groups of the RICS cost-planning standard NRM1, read in the order a house is built: preliminaries, substructure, frame and upper floors, roof, stairs, external walls, windows and external doors, internal walls and doors, finishes, services and external works. Contractors sometimes order a bill by trade instead (excavation, concrete, masonry and so on) to match subcontract packages; element order is easier to follow for a house.
Example: bill of quantities for a 3-bedroom house
The example workbook has quantities for a single-storey three-bedroom house of 110 m², worked out from the assumptions below so you can follow every figure. Add your own rates.
Assumptions: 11.0 × 10.0 m single-storey footprint (110 m² gross floor area); 230 mm masonry external walls, 3.0 m storey height, 42 m external perimeter; about 20 m of internal load-bearing walls and 35 m of partitions; 600 × 300 mm strip footings in trenches 900 mm deep; 100 mm ground slab on 150 mm hardcore; pitched roof at 30° with 0.5 m overhangs; 8 windows of 1.2 × 1.2 m and 2 of 0.6 × 0.6 m; 2 external and 7 internal doors; 2 bathrooms.
| Section | Item | Qty | Unit | How it's worked out |
|---|---|---|---|---|
| Substructure | Excavate foundation trenches | 34 | m³ | 62 m of trench × 0.6 × 0.9 m |
| Concrete in strip footings | 11 | m³ | 62 m × 0.6 × 0.3 m | |
| Foundation walling to damp-proof course | 37 | m² | 62 m × 0.6 m high | |
| Damp-proof course | 62 | m | Wall length on footings | |
| Hardcore bed 150 mm | 15 | m³ | About 102 m² internal × 0.15 m | |
| Ground-floor slab 100 mm | 102 | m² | Internal floor area | |
| Roof | Roof structure and covering (on slope) | 152 | m² | 12 × 11 m plan with overhangs = 132 m², ÷ cos 30° |
| Fascia and gutter | 46 | m | Eaves and verge perimeter | |
| External walls | Masonry walls, net of openings | 110 | m² | 42 m × 3.0 m = 126 m², less about 16 m² of openings |
| Windows and external doors | Windows | 10 | nr | 8 at 1.2 × 1.2 m, 2 at 0.6 × 0.6 m |
| External doors | 2 | nr | ||
| Internal walls and doors | Partitions, net of openings | 93 | m² | 35 m × 3.0 m, less 7 door openings |
| Internal doorsets | 7 | nr | 3 bedrooms, 2 bathrooms, kitchen, store | |
| Internal finishes | Wall plaster | 290 | m² | Inside face of external walls + both faces of partitions |
| Wall tiling to wet areas | 40 | m² | 2 bathrooms + kitchen splashback | |
| Floor screed and finish | 102 | m² | ||
| Ceilings | 102 | m² | ||
| Painting to walls and ceilings | 390 | m² | Plaster + ceilings | |
| Services | Sanitary fittings | 7 | nr | 2 WC, 2 basins, 1 shower, 1 bath, 1 kitchen sink |
| Electrical points | 45 | nr | Lights, sockets and switches (provisional) |
Illustrative only, not taken from a real drawing: measure your own design. Rates are left blank because prices vary too much by country to quote one; the construction cost estimator has sourced default rates for eight countries.
BOQ vs bill of materials vs cost estimate
A BOQ measures the work so contractors can price it; a bill of materials lists the materials to buy; a cost estimate is an early approximation from floor area or elemental rates before the design is detailed.
| Document | What it lists | Used for |
|---|---|---|
| Bill of quantities (BOQ) | Measured items of work with units and quantities; rates cover labour, plant, materials, overhead and profit | Tendering, comparing bids, valuing variations and payments |
| Bill of materials (BOM) | Materials and components to buy | Ordering and controlling waste |
| Cost estimate | Approximate cost from area or elemental rates | Early budgeting, before detailed design |
| Schedule of rates | Unit rates with no firm quantities | Term or framework work measured as it's done |
Sources: Designing Buildings, bills of quantity, bill of quantities v schedule of rates, CivilQuants, BOQ vs BOM.
Measurement standards for a BOQ by country
Quantities in a formal BOQ are measured to a published standard so every tenderer prices the same thing: NRM2 for building work in the UK, CESMM4 for civil engineering, IS 1200 in India and the ASAQS system in South Africa.
| Where | Standard |
|---|---|
| UK, building | RICS NRM2, detailed measurement for building works; replaced SMM7 in 2013 |
| UK and international, civils | ICE CESMM4, civil engineering standard method of measurement |
| International | RICS POMI, principles of measurement (international) |
| India | BIS IS 1200, method of measurement of building and civil engineering works |
| South Africa | ASAQS, standard system of measuring building work |
On a small house you don’t need the full rules, but measure consistently: net quantities, one unit per item, and openings deducted from wall areas.
Who prepares a bill of quantities?
Usually the client's quantity surveyor; on small houses the architect, engineer or builder often prepares a simpler one, and contractors price it.
RICS lists preparing bills of quantities under NRM2 as a standard quantity surveying service (RICS quantity surveyor services). Once the job is won, the priced BOQ becomes the budget: in Aaghaz360 you can track spend against it phase by phase.
Frequently asked questions
What is a BOQ in construction?
A bill of quantities (BOQ) is an itemised document listing every measured item of work, with its description, unit and quantity, so that every contractor prices the same scope. It is usually prepared by a quantity surveyor from complete drawings and specifications, and the priced BOQ is then used to compare tenders, value variations and work out interim payments and the final account.
How do I prepare a BOQ in Excel?
Set up columns for item reference, description, unit, quantity, rate and amount, with amount = quantity × rate. Group the rows into sections such as preliminaries, substructure, superstructure, finishes, services and external works, each with a total. Take the quantities off the drawings using one method of measurement, add provisional sums, prime cost sums and contingency, and carry every section total to a summary. This template is already set up that way.
What is the standard BOQ format?
Measured-work pages are ruled item, description, quantity, unit, rate and amount. Preliminaries, collection and summary pages show amounts only. A full bill usually runs: preliminaries, preambles, measured work by element or trade, provisional sums, prime cost sums, daywork and the summary.
How do you calculate a BOQ?
Measure each quantity from the drawings (length, area, volume or count) using the rules of your method of measurement, such as NRM2 in the UK or IS 1200 in India. Multiply each quantity by its unit rate to get the amount, total each section, then add preliminaries, provisional and prime cost sums, contingency and any tax that applies.
What is the difference between a BOQ and a BOM?
A bill of quantities measures the work for pricing and tendering, and its rates cover labour, plant, materials, overhead and profit. A bill of materials lists the materials and components to buy, for ordering. Both can come from the same take-off.
Is a BOQ the same as a cost estimate?
No. A cost estimate is an early approximation, usually from floor area or elemental rates before the design is detailed. A BOQ is a detailed, measured document prepared once the design is complete and priced by contractors. A priced BOQ gives the most accurate estimate, but an estimate can't replace a BOQ in a tender.
Who prepares the bill of quantities?
Usually the client's quantity surveyor or cost consultant; RICS lists preparing bills of quantities as a standard quantity surveying service. On small houses the architect, engineer or builder often prepares a simpler one, and contractors price it.
What are provisional sums and prime cost sums in a BOQ?
A provisional sum is an allowance for work that can't be fully described yet; under NRM2 it is either defined or undefined. A prime cost (PC) sum is a supply-only allowance for goods not yet chosen, such as tiles at a set price per square metre, to which the contractor adds fixing and profit. The template has lines for both in the summary.