Free BOQ Template for Building Construction (Excel)

Download a free bill of quantities (BOQ) template in Excel, ready for a house or small building. Rate and amount work out themselves, each section totals to a summary with overhead, provisional sums, contingency and tax, and there is a filled example for a three-bedroom house. No email or sign-up.

By Aaghaz360 teamReviewed

Download the BOQ template

Excel (.xlsx), works in Excel, Google Sheets, Numbers and LibreOffice.

Rather price it online? The free BOQ generator fills in default material and labour rates for eight countries and exports a priced BOQ to Excel.

Open the BOQ generator

What's in the BOQ template

One Excel sheet with the standard BOQ columns, eleven house sections in build order, live formulas for rate, amount and section totals, and a summary that adds overhead, provisional sums, contingency and tax.

  • Columns: Ref, Description, Unit, Qty, Material rate, Labour rate, Rate (material + labour), Amount (qty × rate) and Notes.
  • Sections: Preliminaries, Substructure, Frame and upper floors, Roof, Stairs, External walls, Windows and external doors, Internal walls and doors, Internal finishes, Services, External works.
  • Summary: each section total, overhead and profit (%), provisional sums for fees and utility connections, a prime cost sum, contingency (%) and tax (%).
  • Shaded cells are the ones you fill. Everything else calculates, so add or delete rows inside a section and the totals still hold.

How to prepare a BOQ in Excel

Measure each item from the drawings, enter the quantity and unit, price it with a material and a labour rate, and let each section total carry to the summary, where you add overhead, provisional sums, contingency and tax.

  1. Fill in the project details and choose your currency before you download.
  2. Take off quantities from the drawings, section by section, using one method of measurement. Measure net: wall area less openings, for example.
  3. Enter a material rate and a labour rate per unit from supplier and subcontractor quotes. The template adds them and works out the amount.
  4. Add provisional sums for work you can’t describe yet and prime cost sums for items not chosen yet, such as kitchen units.
  5. Set overhead, contingency and tax percentages in the summary. The total updates as you go.

Our guide to quantity takeoff and unit costs works through a foundation example step by step.

Standard BOQ format

A bill of quantities lists each item of work with a reference, a description, a unit, a quantity, a rate and an amount, grouped into sections whose totals carry to a summary.

Standard BOQ columns
ColumnWhat goes in it
RefA unique item reference, such as B.3
DescriptionWhat the work is, referring to the specification rather than repeating it
Unitm, m², m³, t, nr (number), item or hour
QuantityMeasured net from the drawings
RateThe price per unit, entered by whoever prices the bill
AmountQuantity × rate, totalled per section

A full bill also has preliminaries (the contractor’s site-wide costs such as set-up, supervision and insurance), provisional and prime cost sums, daywork rates for unmeasured work, and a summary (BOQ format conventions).

BOQ sections for a house, in build order

The template follows the element groups of the RICS cost-planning standard NRM1, read in the order a house is built: preliminaries, substructure, frame and upper floors, roof, stairs, external walls, windows and external doors, internal walls and doors, finishes, services and external works. Contractors sometimes order a bill by trade instead (excavation, concrete, masonry and so on) to match subcontract packages; element order is easier to follow for a house.

Example: bill of quantities for a 3-bedroom house

The example workbook has quantities for a single-storey three-bedroom house of 110 m², worked out from the assumptions below so you can follow every figure. Add your own rates.

Assumptions: 11.0 × 10.0 m single-storey footprint (110 m² gross floor area); 230 mm masonry external walls, 3.0 m storey height, 42 m external perimeter; about 20 m of internal load-bearing walls and 35 m of partitions; 600 × 300 mm strip footings in trenches 900 mm deep; 100 mm ground slab on 150 mm hardcore; pitched roof at 30° with 0.5 m overhangs; 8 windows of 1.2 × 1.2 m and 2 of 0.6 × 0.6 m; 2 external and 7 internal doors; 2 bathrooms.

Illustrative quantities for a 110 m² three-bedroom house
SectionItemQtyUnitHow it's worked out
SubstructureExcavate foundation trenches34m³62 m of trench × 0.6 × 0.9 m
Concrete in strip footings11m³62 m × 0.6 × 0.3 m
Foundation walling to damp-proof course37m²62 m × 0.6 m high
Damp-proof course62mWall length on footings
Hardcore bed 150 mm15m³About 102 m² internal × 0.15 m
Ground-floor slab 100 mm102m²Internal floor area
RoofRoof structure and covering (on slope)152m²12 × 11 m plan with overhangs = 132 m², ÷ cos 30°
Fascia and gutter46mEaves and verge perimeter
External wallsMasonry walls, net of openings110m²42 m × 3.0 m = 126 m², less about 16 m² of openings
Windows and external doorsWindows10nr8 at 1.2 × 1.2 m, 2 at 0.6 × 0.6 m
External doors2nr
Internal walls and doorsPartitions, net of openings93m²35 m × 3.0 m, less 7 door openings
Internal doorsets7nr3 bedrooms, 2 bathrooms, kitchen, store
Internal finishesWall plaster290m²Inside face of external walls + both faces of partitions
Wall tiling to wet areas40m²2 bathrooms + kitchen splashback
Floor screed and finish102m²
Ceilings102m²
Painting to walls and ceilings390m²Plaster + ceilings
ServicesSanitary fittings7nr2 WC, 2 basins, 1 shower, 1 bath, 1 kitchen sink
Electrical points45nrLights, sockets and switches (provisional)

Illustrative only, not taken from a real drawing: measure your own design. Rates are left blank because prices vary too much by country to quote one; the construction cost estimator has sourced default rates for eight countries.

BOQ vs bill of materials vs cost estimate

A BOQ measures the work so contractors can price it; a bill of materials lists the materials to buy; a cost estimate is an early approximation from floor area or elemental rates before the design is detailed.

BOQ compared with similar documents
DocumentWhat it listsUsed for
Bill of quantities (BOQ)Measured items of work with units and quantities; rates cover labour, plant, materials, overhead and profitTendering, comparing bids, valuing variations and payments
Bill of materials (BOM)Materials and components to buyOrdering and controlling waste
Cost estimateApproximate cost from area or elemental ratesEarly budgeting, before detailed design
Schedule of ratesUnit rates with no firm quantitiesTerm or framework work measured as it's done

Sources: Designing Buildings, bills of quantity, bill of quantities v schedule of rates, CivilQuants, BOQ vs BOM.

Measurement standards for a BOQ by country

Quantities in a formal BOQ are measured to a published standard so every tenderer prices the same thing: NRM2 for building work in the UK, CESMM4 for civil engineering, IS 1200 in India and the ASAQS system in South Africa.

BOQ measurement standards
WhereStandard
UK, buildingRICS NRM2, detailed measurement for building works; replaced SMM7 in 2013
UK and international, civilsICE CESMM4, civil engineering standard method of measurement
InternationalRICS POMI, principles of measurement (international)
IndiaBIS IS 1200, method of measurement of building and civil engineering works
South AfricaASAQS, standard system of measuring building work

On a small house you don’t need the full rules, but measure consistently: net quantities, one unit per item, and openings deducted from wall areas.

Who prepares a bill of quantities?

Usually the client's quantity surveyor; on small houses the architect, engineer or builder often prepares a simpler one, and contractors price it.

RICS lists preparing bills of quantities under NRM2 as a standard quantity surveying service (RICS quantity surveyor services). Once the job is won, the priced BOQ becomes the budget: in Aaghaz360 you can track spend against it phase by phase.

Frequently asked questions

What is a BOQ in construction?

A bill of quantities (BOQ) is an itemised document listing every measured item of work, with its description, unit and quantity, so that every contractor prices the same scope. It is usually prepared by a quantity surveyor from complete drawings and specifications, and the priced BOQ is then used to compare tenders, value variations and work out interim payments and the final account.

How do I prepare a BOQ in Excel?

Set up columns for item reference, description, unit, quantity, rate and amount, with amount = quantity × rate. Group the rows into sections such as preliminaries, substructure, superstructure, finishes, services and external works, each with a total. Take the quantities off the drawings using one method of measurement, add provisional sums, prime cost sums and contingency, and carry every section total to a summary. This template is already set up that way.

What is the standard BOQ format?

Measured-work pages are ruled item, description, quantity, unit, rate and amount. Preliminaries, collection and summary pages show amounts only. A full bill usually runs: preliminaries, preambles, measured work by element or trade, provisional sums, prime cost sums, daywork and the summary.

How do you calculate a BOQ?

Measure each quantity from the drawings (length, area, volume or count) using the rules of your method of measurement, such as NRM2 in the UK or IS 1200 in India. Multiply each quantity by its unit rate to get the amount, total each section, then add preliminaries, provisional and prime cost sums, contingency and any tax that applies.

What is the difference between a BOQ and a BOM?

A bill of quantities measures the work for pricing and tendering, and its rates cover labour, plant, materials, overhead and profit. A bill of materials lists the materials and components to buy, for ordering. Both can come from the same take-off.

Is a BOQ the same as a cost estimate?

No. A cost estimate is an early approximation, usually from floor area or elemental rates before the design is detailed. A BOQ is a detailed, measured document prepared once the design is complete and priced by contractors. A priced BOQ gives the most accurate estimate, but an estimate can't replace a BOQ in a tender.

Who prepares the bill of quantities?

Usually the client's quantity surveyor or cost consultant; RICS lists preparing bills of quantities as a standard quantity surveying service. On small houses the architect, engineer or builder often prepares a simpler one, and contractors price it.

What are provisional sums and prime cost sums in a BOQ?

A provisional sum is an allowance for work that can't be fully described yet; under NRM2 it is either defined or undefined. A prime cost (PC) sum is a supply-only allowance for goods not yet chosen, such as tiles at a set price per square metre, to which the contractor adds fixing and profit. The template has lines for both in the summary.

Turn your BOQ into a tracked budget